    World Tunnel Congress, 2022
Publish : Sept 2022, 08
         
       Mr. Dilandra Pathak completed the visit to Copenhagen, Denmark. 
       He learnt the following lessions from World Tunnel Congress, 2022.
       
 
    - In underground projects Geological Baseline Report (GBR) shall be included as a major part of the contract.
 - Prior to construction of every underground project, 10-12% of project cost shall be invested for realistic assessment of the project to reduce the Underground Uncertainty.
 - The owner owns the ground and is responsible for weak conditions and the contractor shall also get benefit from good ground. So risk sharing must be equal to both parties.
 - The engineer shall be responsible for the design fault. But the client must conduct required, investigation, design modeling works as per the requirements of Project.
 - Horizontal drilling can replace the excavation of test tunnels. A Norwegian company completes 2100m of horizontal drilling from one point.
 - Grouting technology is much advanced now.
 - The Danish society is controlled by rule of Law and financial inequalities are almost negligible.